Spinal Injury Rehabilitation Center, Chitwan Unit
Global Grant
Fighting disease
2025-26
2,703,419
Grant Amount
Project Details
Description
95% works completed, few equipment remaining to install. 8 staff sent to SIRC, Sanga for the 1 month training. 3-phase electricity network connection started, elevator design and installation initiated with RC Chitwan's internal fund, Plan to inaugurate the project on 3rd December 2025.
Location
Bharatpur-3, Narayangarh, Chitwan
Month
September
Grant Amount
2,703,418.78
Fiscal Year
2025-26
Added On
September 2, 2025
Cost Breakdown
| Item | Description | Amount |
|---|---|---|
| Therapy, Laboratory, ICT equipment | 2,703,418.78 | |
| Total | 2,703,418.78 | |
Global Grant Information
Project Status
CompletedFunding Type
Rotary Global Grant Funded
Club Information
Related Projects
Hemodialysis Center
2025-26
Spinal Injury Rehabilitation Center, Chi...
2025-26